The leader in charge of the bureau led the team to the construction site, listened to the introduction of the project development and construction by the head of the project department in detail, focused on understanding the current “roadblock” dilemma and difficulties of the enterprise and the project, and put forward targeted help suggestions; Set up a comprehensive window of “one thing for construction and completion” to provide one-stop approval services such as professional technical guidance, project handling guidance, consultation and coordination for project commencement and completion.
Adhere to the whole-process specialized service, make good use of process reengineering, data sharing, whole-process online, accurate service and other measures, and accelerate the completion of the commencement and completion of guaranteed land supply projects.
Source: Linping Residential Construction.
.
Issue the Implementation Opinions on Encouraging Construction Projects to Remain at Work and Stable Positions by “Striving for Economy, Striving for Development, and Striving to Achieve a Good Start”, issue relevant subsidy policies, and circulate a notice of commendation for projects that do not stop work during the Spring Festival and return to work ahead of schedule; The construction workers who meet the subsidy standard will be granted a financial subsidy of 300 to 500 yuan; The construction units that meet the standards shall be granted a maximum of 500000 yuan of financial subsidies.
On the eighth day of the first month, a mobilization meeting for the resumption of work and production of construction projects in Linping District was held to accelerate the resumption of work and production of construction sites in the whole district after the holiday.
Implement full-cycle project-based management, assign special personnel to precisely meet project requirements, ensure the commencement of early projects, grasp the progress of projects under construction, and ensure the use of completed projects.
Go to work immediately after the holiday.
Do a good job in the inspection of safe production and civilized construction, focusing on the review of deep foundation pit construction, lifting machinery, tall formwork support, construction power, etc; Timely grasp the situation of resumption of work and production of construction sites within the jurisdiction and the existing difficulties and problems, help enterprises solve problems, and help enterprises resume production.
Make overall plans and do a good job in the preliminary work.
Plan early and arrange early.
Deepen service and optimize business environment.
Before the year, organize all project responsible units to arrange the machinery, personnel and funds for resumption of work in advance to ensure resumption of work upon receipt of leave.
According to the plan, the construction sites in the region will be fully resumed before February 5.
In the new year, Linping is full of vitality, and the District Housing and Urban-Rural Development Bureau will seize the opportunity and work hard to take the lead in combination with the actual situation of the district, lay a solid foundation for the realization of the two goals of 100% economic and social development of the district’s construction sites before February 5 and reaching production capacity, and fully promote the improvement of the quality and efficiency of the industry development management, and ensure that the economic indicators of housing and construction are “good at the beginning”, “red every quarter” and “red throughout the year”.
As of January 30, of the 242 projects in the region, 40 projects have been resumed, with a resumption rate of 16.53%.
Take multiple measures to ensure the construction progress.
At the beginning of the new year, Linping District made the project construction plan for the first quarter and the whole year of 2023 in a timely manner based on the idea of “decisive battle at the beginning and sprint at the beginning”.