Common quality problems of building electrical embedment


First look at the drawing, and then describe: the labor team leader who does this work is considered as follows: when the wall wire vertical pipe is embedded in the wallboard, the wire pipe larger than the drawing design shall be used, and the wall shall be embedded before sealing

.

When laying the top plate conduit, insert the conduit model according to the drawing design requirements into the larger conduit

.

This can save the material cost of the pipe joint for the general contractor, save the working time and speed up the progress (good work)

.

The first thing to be sure is that the labor team leader must have thought out a way to solve this problem

.

He thinks that this method can save time and effort, improve work efficiency, and save the cost of pipe joints for the general contractor (the original intention is good)

.

reflection? 1

.

He saved the pipe joint, so he wasted the pipe? (the line pipe should be more valuable than the pipe joint.) 2

.

Will the pipe be blocked when dusting? (the team leader said that if the joint was wrapped with tape, it would not be blocked, but wouldn’t it waste tape for the general contractor? And will wrapping tape waste work? Can’t it be blocked by wrapping tape? If it’s blocked, isn’t it more wasteful 3

.

Is it easy to wear steel wire and wire in the later stage? Is it a waste of work? 4

.

Will the supervisor of Party A agree with him when checking and accepting the roof? Will he be allowed to rework after dismantling? 5

.

If the final result is that the general contractor thinks that labor is wasting materials, and the supervisor of Party A thinks that the general contractor is operating in violation of regulations, will the reputation of the labor team be affected? The general contractor will also follow suit, which will affect the reputation of the general contractor

.

Angle: different positions and different perspectives

.

In view of this matter, I think labor, general contractor and Party A’s supervisor must have their own ideas and practices

.

I don’t know if this kind of situation has ever occurred in the projects where we work? What do you think? How do you do it or how do you ask for it? [communicate with each other and make progress together] College of hydropower technology 1 course fund initial course entering class 2 course stock initial course entering class 3 course insurance training camp entering class 4 course fund advanced practical course entering class 5 course zero basic financial management entering class 6 course how to choose potential fund entering class 7 course CAD entering class Door to proficient into the classroom 8 courses stock advanced courses into the classroom 9 courses building water supply and drainage drawing into the classroom 10 courses building electrical drawing into the classroom 11 courses Mitsubishi PLC teaching into the classroom 12 courses indoor water and electricity design course into the classroom! Click “watching” 👇🏻 , check in and clock out! Thank you for reading this article.

.