The completion report of the construction unit should include the following main contents: the situation of the completed project, technical archives and construction management data, verification and spot check results of safety and main usage functions, visual quality acceptance results, and self inspection conclusions of the project quality.
The construction unit shall submit a completion acceptance application to the supervising unit 15 days before the completion acceptance.
The supervising unit shall approve the construction unit’s engineering re inspection application within 3 days.
After receiving the application, the supervising unit shall organize preliminary acceptance.
The residential part shall be subject to household acceptance in accordance with the Provisional Regulations on the Management of Household Acceptance of Residential Construction Engineering Quality in Shanxi Province.
The supervising engineer shall organize relevant units and personnel in a timely manner in accordance with the acceptance standards to conduct on-site review of the quality acceptance record forms for inspection batches, sub projects, and sub projects submitted by the construction unit, and conduct acceptance of the construction quality; 4.
It is necessary to have complete engineering quality assessment materials, completion drawings, and engineering technical archives.
After the quality of inspection batches, sub projects, and sub projects has passed the acceptance, the supervising engineer should promptly sign and confirm the relevant documents before proceeding to the next process of construction.
Construction of the next process is not allowed for processes that have not been signed and approved; 5.
The completion acceptance time, location, and personnel shall be reported in writing to the Quality Supervision Department 7 days before the acceptance, and the rectification shall be completed according to the rectification opinions within 7 days after the acceptance, and the “Construction Unit Project Completion Acceptance Report” shall be submitted.
1) After completing all the design documents and contract agreements, the construction unit shall conduct a self inspection and prepare a completion report, which shall be signed and stamped by the project manager and technical leader, and then submitted to the supervision unit
.
The Engineering Management Department is responsible for inviting the Quality Supervision Department to participate in the acceptance.
Only after passing the review of the supervision and engineering management department can the construction unit submit a completion acceptance application.
If the acceptance is not qualified, the supervising engineer shall notify the construction unit to carry out rework or repair.
After passing the self inspection by the construction unit, fill out the engineering inspection form and the relevant inspection batch or sub item/sub item engineering quality acceptance record form, and apply for inspection to the supervisor; 3.
Inspection lot, sub item, sub item, and quality acceptance system 1.
The rectification requirements proposed in the preliminary acceptance shall be fully completed and approved by the preliminary acceptance team (supervision, construction unit, design, survey, and property management company).
After completion of inspection lot, sub item, and sub item projects, the construction unit conducts self inspection according to the project quality acceptance standards; 2.
Construction engineering data Construction engineering information exchange 61 original contents official account [transfer] Four steps to understand the whole process of building acceptance 1.
After passing the self inspection, the acceptance shall be reorganized; 2、 Unit project completion acceptance: 1.
The construction unit must cooperate with the internal personnel of the engineering management department to organize and bind complete completion materials before the preliminary acceptance.
2.