13 special acceptance items that must be done in construction engineering! What do you have?


Source: Based on the engineering projects in a certain area, Luban alliance of construction engineering summarizes 13 special acceptance items that need to be carried out in construction projects according to the relevant national and local regulations, so as to see what they are? (Note: due to different requirements for special acceptance in different regions, please refer to the regulations of local authorities.) 01 planning line inspection and acceptance conditions: if the site of the project meets the conditions of “three supplies and one leveling”, the construction unit shall entrust a qualified surveying and mapping organization to set out the line and issue a report on the survey results of the construction project

.

·Acceptance procedure the construction unit shall submit the completed application form for line inspection of construction project (attached with the report on survey results of construction project) to the planning administrative department before construction, and the planning supervision and inspection personnel shall inspect the construction site and carry out subsequent construction only after obtaining permission

.

02 planning acceptance · acceptance conditions: the main body and facade of the construction project have been completed, the construction unit has entrusted a qualified surveying and mapping agency to conduct surveying and mapping, and issued the report on the completion survey results of the construction project

.

The outdoor road, pipe network and landscaping have been completed

.

·Acceptance procedure 1) after the construction unit or individual has completed all construction and environmental construction according to the contents approved by the construction project planning license, it shall fill in the declaration form for acceptance of construction project planning and apply to the planning administrative department for acceptance of planning according to the regulations

.

2) The planning supervision and inspection personnel shall inspect the construction site, and if they pass the acceptance, the planning administrative department shall sign on the appendix of the planning permit

.

03 elevator acceptance · acceptance conditions elevator installation, transformation and major maintenance are completed and passed the self inspection of the construction unit

.

·Acceptance procedure 1) the elevator user shall apply to the inspection organization for acceptance inspection with the approved commencement report and relevant data

.

The elevator inspection and testing institution shall arrange the inspection within 10 working days from the date of receiving the inspection application

.

2) After the installation and transformation of the elevator and passing the inspection, the safety supervision organization shall go through the registration procedures and issue the elevator safety inspection mark

.

04 fire protection acceptance · acceptance conditions: the linkage debugging of indoor fire compartment (including blocking), fire protection (rolling shutter) door, fire hydrant, sprinkler (gas) fire extinguishing, fire indicator, fire alarm, electrical and other systems has been completed, and the fire protection structure of outdoor curtain wall, courtyard ring Road, outdoor connector, etc

.

has been completed, and self inspection has been qualified

.

The construction unit entrusts a qualified fire testing institution to test and issue a fire testing report

.

·Acceptance procedure 1) the construction unit shall provide the following materials when applying for fire acceptance: A

.

application form for fire acceptance of construction project; B

.

acceptance report of project completion; C

.

certificate of fire product quality; D

.

certificate and ex factory certificate of building components, building materials and interior decoration materials with fire performance requirements meeting national or industrial standards; e

.

fire facilities F

.

legal identity certificate and qualification level certificate of construction, engineering supervision and testing units; g

.

other materials required by law

.

2) The local public security fire protection institution shall conduct on-site fire protection acceptance, and issue fire protection approval documents if the acceptance is qualified

.

05 civil air defense acceptance acceptance conditions: the underground civil air defense project has completed the installation of ventilation, lamps and civil air defense doors, and passed the self inspection

.

For example, if the outdoor opening and “three defense equipment” of civil air defense project do not meet the conditions, the construction delay certificate and temporary no installation certificate can be issued

.

·Acceptance procedure: the construction unit shall organize the completion acceptance, inform the local civil air defense engineering quality supervision organization or civil air defense competent department in writing 7 days in advance to participate in the supervision, and file with the civil air defense competent department at or above the county level in the place where the project is located 15 days after the acceptance

.

Acceptance conditions of indoor environment: 1) after the design content of indoor decoration is completed, the construction unit entrusts a qualified environmental testing agency and signs a contract; 2) when the concentration of free formaldehyde, benzene, ammonia and total volatile organic compounds (TVOC) in the indoor environment of civil construction projects is detected, the civil construction projects with central air conditioning should be carried out under the condition of normal operation of air conditioning; 3) when the concentration of free formaldehyde, benzene, ammonia and total volatile organic compounds (TVOC) in the indoor environment of civil construction projects is detected, the civil construction projects with central air conditioning For civil construction projects with natural ventilation, the detection should be carried out one hour after the external doors and windows are closed; 3) for civil construction projects with central air conditioning, the detection of radon concentration in indoor environment should be carried out under the condition of normal operation of air conditioning; for civil construction projects with natural ventilation, the detection should be carried out 24 hours after the external doors and windows are closed

.

·Acceptance procedures: the construction unit entrusts a qualified environmental testing agency to conduct on-site testing and issue the “indoor environmental pollutant concentration testing report”

.

07 building energy efficiency acceptance · acceptance conditions 1) the contractor has completed the construction contract, and each part of the project has passed the acceptance

.

2) The on-site physical test of the air tightness of the outer window shall be conducted by a qualified testing organization with the witness of the supervision (construction) personnel

.

3) After the installation of heating, ventilation and air conditioning, power distribution and lighting projects, the energy-saving performance of the system shall be tested, and the construction unit shall entrust a testing institution with corresponding testing qualification to test and issue a testing report

.

·Acceptance procedure 1) before the completion acceptance of civil construction projects, the construction unit shall organize the design, construction and supervision units to carry out special acceptance of energy-saving projects, be responsible for the acceptance results, and notify the municipal energy conservation office to supervise on site three days in advance

.

2) The record shall be handled within 10 working days after the acceptance, and the construction unit shall submit the following materials: A

.

civil building energy saving record form; B

.

civil building energy saving special acceptance report; C

.

new wall material special fund payment certificate; D

.

copy of new wall material identification certificate

.

08 barrier free facilities acceptance · acceptance conditions complete the barrier free facilities in the design drawings and pass the self inspection

.

·Acceptance procedures the construction unit of a new, expanded or reconstructed construction project shall, when organizing the completion acceptance of the construction project, simultaneously carry out the acceptance of the barrier free facilities

.

In case of failure to carry out the acceptance as required or failure to pass the acceptance, the competent administrative department of construction shall not go through the filing procedures for the completion acceptance

.

09 power supply acceptance · acceptance conditions the construction and supply units shall complete the design drawings of the power receiving and transmission devices according to the power supply enterprise’s review, and pass the self inspection; and sign the power supply contract

.

10 gas acceptance and acceptance conditions the construction and supply units shall complete the gas supply design drawings and pass the self inspection, and sign the gas supply contract

.

11 water supply acceptance · acceptance conditions: the approved reclaimed water facilities have been jointly debugged and operated normally, the production water supply system pipelines have been installed, washed and disinfected; the construction unit entrusts the qualified water sample detection department to take samples for inspection, issue the water quality detection report, and sign the water supply contract

.

12 lightning protection acceptance · acceptance conditions the lightning protection system of grounding, roof, curtain wall, metal doors and windows shall complete the design contents and pass the self inspection; the construction unit shall entrust the lightning protection testing unit with corresponding qualification to issue the test report

.

·Acceptance procedure: 1) the following materials shall be submitted for the completion acceptance of lightning protection device: A

.

application for completion acceptance of lightning protection device; B

.

design approval of lightning protection device; C

.

qualification certificate and qualification certificate of professional construction unit and personnel of lightning protection engineering; D

.

inspection certificate of lightning protection device issued by the inspection institution whose qualification of lightning protection device is recognized by provincial, autonomous regional and municipal competent authorities E

.

lightning protection device as built drawings and other technical data; F

.

lightning protection product factory certificate, installation record and test report issued by national recognized lightning protection product testing agency

.

2) If the license institution has completed the relevant acceptance procedures and the lightning protection device has passed the acceptance, it shall issue the acceptance certificate of lightning protection device

.

13 pre acceptance and acceptance conditions of project archives the contractor has completed the drawings and construction contract contents, and all divisional works have passed the acceptance, and the engineering data (including as built drawings) are accurate and complete according to the requirements of the interim measures.

.