Administrative Measures for Construction Permit of Building Engineering 【 2021 】


(3) If the construction site has basically met the construction conditions and houses need to be expropriated, the progress shall meet the construction requirements.

The time for examination and approval may be extended accordingly after the supporting documents are completed and corrected; If the conditions are not met, the construction unit shall be notified in writing within seven days from the date of receiving the application, and the reasons shall be explained.

Article 6 The name, location and scale of the project for which the construction unit applies for a construction license shall conform to the construction contract signed according to law.

If the construction unit or construction unit changes during the construction of a construction project, it shall re apply for a construction license.

If there is no public bidding for the project that should be subject to bidding according to the regulations, or if there is no public bidding for the project that should be subject to public bidding, or if the project is contracted by dismemberment, or if the project is contracted to an enterprise that does not have the corresponding qualifications, the determined construction enterprise is invalid.

(5) Where there are fund arrangements, construction drawings and technical data to meet the construction needs, the construction unit shall provide a letter of commitment that the construction funds have been implemented, and the construction drawing design documents have been reviewed as qualified as required.

(2) If the construction project planning license should be obtained according to law, the construction project planning license has been obtained.

(3) After receiving the Application Form for Construction License of Construction Engineering and the attached supporting documents submitted by the construction unit, the license issuing authority shall issue the construction license within seven days from the date of receiving the application if the conditions are met; If the supporting documents are incomplete or invalid, the construction unit shall be informed of all the contents that need to be supplemented and corrected on the spot or within five days.

Article 2 The construction unit that is engaged in the construction, decoration and decoration of various types of housing buildings and their ancillary facilities, and the installation of their supporting lines, pipelines and equipment, as well as the construction of urban municipal infrastructure projects within the territory of the People’s Republic of China shall, before the commencement of construction, comply with the provisions of these Measures, Apply for a construction permit from the competent housing and urban construction department of the local people’s government at or above the county level (hereinafter referred to as the issuing authority) where the project is located.

If the commencement cannot be started on time for some reason, an application for extension shall be submitted to the issuing authority before the expiration of the period, and the reasons shall be explained; The extension shall be limited to two times, and each time shall not exceed three months.

The competent housing and urban construction departments of the local people’s governments at or above the county level shall not, in violation of laws and regulations, add other conditions for obtaining construction permits.

The report shall include the time, reason, location under construction, maintenance management measures, etc.

The construction permit shall be placed on the construction site for future reference and disclosed on the construction site as required.

The Administrative Measures for Construction Permit of Construction Projects was issued by Decree No.

Lifting Anchor

18 of the Ministry of Housing and Urban Rural Development on June 25, 2014; Revised by Decree No.

The competent housing and urban construction departments of the people’s governments of provinces, autonomous regions and municipalities directly under the Central Government may adjust the quota according to the actual local conditions and report it to the competent housing and urban construction department under the State Council for the record.

Construction projects with an investment of less than 300000 yuan or a building area of less than 300 square meters may not apply for a construction permit.

When a construction project resumes construction, it shall report to the license issuing authority; Before resuming the construction of a project that has been suspended for one year, the construction unit shall report to the license issuing authority for verification of the construction permit.

Article 5 To apply for a construction permit, the following procedures shall be followed: (1) The construction unit shall obtain the Application Form for Construction Permit of Construction Engineering from the license issuing authority.

Article 4 When applying for a construction license, the construction unit shall meet the following conditions and submit the corresponding supporting documents: (1) If the land use approval formalities should be gone through according to law, the land use approval formalities for the construction project have been gone through.

For highly professional engineering projects, special quality and safety construction organization design has been prepared, and engineering quality and safety supervision procedures have been handled according to regulations.

(6) There are specific measures to ensure project quality and safety.

Article 3 The construction projects that should apply for the construction license according to these Measures shall not be started without the construction license.

Article 7 The construction permit shall not be forged or altered.

42 of the Ministry of Housing and Urban Rural Development of September 28, 2018, Decision of the Ministry of Housing and Urban Rural Development of the People’s Republic of China on Amending the Administrative Measures for Construction Permit of Construction Projects; The Measures are formulated in accordance with the Construction Law of the People’s Republic of China in order to strengthen the supervision and management of construction activities, maintain the order of the construction market, and ensure the quality and safety of construction projects, as amended in Article 1 of the Decision of the Ministry of Housing and Urban Rural Development of March 30, 2021 on Amending the Three Regulations Including the Administrative Measures for Construction Permit of Construction Projects (Order No.

No unit or individual may divide the project that should be applied for a construction license into several projects below the quota to avoid applying for a construction license.

Article 10 The license issuing authority shall publicize the basis, conditions, procedures, time limit for applying for the construction license, all materials to be submitted and the application model, etc.

(2) The construction unit shall submit an application to the license issuing authority with the Application Form for Construction Permit of Construction Engineering affixed with the seal of the unit and legal representative and the supporting documents specified in Article 4 of these Measures.

Establish the project quality and safety responsibility system and implement it to specific personnel.

If the construction is neither started nor applied for extension, or the number and time limit of extension are exceeded, the construction permit shall be automatically invalidated.

of the suspension of construction, and shall do a good job in the maintenance and management of the construction project in accordance with the provisions.

Article 8 The construction unit shall start construction within three months from the date of obtaining the construction permit.

Article 9 Where the construction of a construction project under construction is suspended for some reason, the construction unit shall report to the license issuing authority within one month from the date of suspension of construction.

The construction organization design prepared by the construction enterprise includes corresponding quality and safety technical measures based on the characteristics of the construction project.

The construction project that has approved the commencement report according to the limits of authority and procedures prescribed by the State Council will no longer receive a construction permit.

(4) The construction enterprise has been determined.

in the office and relevant websites..

52 of the Ministry of Housing and Urban Rural Development).