The Project Department shall further sort out and deepen the approval process nodes, corresponding levels and responsible persons of the project’s major dangerous project plans and other plans in combination with national laws and regulations and the requirements of the government under its jurisdiction, so as to ensure the legality and compliance of all management links of the major dangerous project# 02 Risk identification and prompt shall be well done for dangerous and large projects to ensure the comprehensiveness of scheme disclosure.
At the same time, several suggestions are put forward for the follow-up safety production management of the project: # 01 should attach great importance to safety management and system construction to ensure the compliance of the scheme and system.
Jiang Hua, Senior Manager of Safety Supervision Department of CSCEC, Chen Jie, Manager of Safety Department of Southwest Bureau of CSCEC, Gao Peng, Deputy General Manager of CSCEC Fifth Engineering Bureau and General Manager of Northwest Branch, Feng Tao, General Manager of Safety Supervision Department, Li Can, Executive Deputy General Manager of Southwest Branch, Jia Xianguo, General Manager and Deputy Secretary of the Party Committee of the three companies, Yang Tianqi, Safety Director of the three companies, and Jiang Zhongxin, Secretary of the Party Committee and General Manager of Sichuan Branch of the three companies participated in the inspection.
It can be included in this inspection list, which fully reflects the concern and attention of SASAC to the work safety of China Construction Fifth Engineering Bureau.
After the on-site inspection, the patrol inspection team checked the office work data and held an exchange discussion with the project personnel.
At the summary and feedback meeting, the patrol inspection team affirmed the overall safety control level, safe and civilized construction, green construction and rapid construction of the project.
At the same time, the project department focuses on new processes, new technologies and new methods, adheres to accurate planning, rapid interpenetration, high standard management and high-quality construction, and constantly improves the level of safety and quality standardization management..
While ensuring production and construction with high quality, we should highlight the management concept of “people-oriented and green construction” to create a safe, intelligent, ecological, harmonious and civilized construction environment.
The first phase project of Jinjiang Cultural and Creative Industry Center of the Third Company is a super high-rise key public construction project in Jinjiang District, Chengdu City, which is more than 200 meters long.
Qin Zhenggang, General Manager of the Safety Supervision Department of China Railway Construction Group Co., Ltd., Chi Lixin, Deputy General Manager of the Safety Supervision Department of CCCC First Harbor Engineering Co., Ltd., Sun Changzhong, Deputy General Manager of China Gezhouba Group International Engineering Co., Ltd., Liu Shun, Head of the Safety Supervision Department of the Installation Branch of China MCC20 Group Co., Ltd., and Lin Weichao, Deputy Head of the Safety Department of China Railway Urban Construction Beijing Co., Ltd.
This project is the first batch of pilot projects of the non road mobile machinery supervision system of Chengdu Housing and Urban Rural Development Bureau, the first batch of green benchmark construction sites in Chengdu, and the “top ten” construction sites for dust pollution prevention and control in Chengdu.
After completion, it will become an important landmark in Jinjiang District.
In the conference room, the patrol inspection team listened to the project’s reports on the project overview, the three-year action of special rectification of work safety, the management and control of major dangerous projects, and the prevention and control of the new epidemic.
Gao Peng, on behalf of China Construction Fifth Engineering Bureau, welcomed all leading experts.
The project has a total of four towers, with a total floor area of 246000 square meters.
The construction scheme of dangerous large projects shall strictly implement the requirements of double disclosure and three-level disclosure system.
Identify the existing problems, dig the root of the problems, and ensure that the investigation, rectification and work effect are in place.
During the period, the implementation of the management and control of major dangerous projects, emergency management of extreme weather, and management of dangerous operations were mainly inspected.
He said that under the overall arrangement of the Group, the Fifth Engineering Bureau of CSCEC vigorously promoted the three-year action of special rectification of production safety, implemented the “16 word policy” of safety management, and strengthened the systematization, refinement, informatization and intelligence of safety management.
At the same time, the project management plan shall be updated, adjusted and improved regularly to ensure that the construction plan matches the construction site and that the plan can be implemented to ensure safety.
inspected the Jinjiang Cultural and Creative Industry Phase I Project.
In order to strengthen the safety control of major dangerous projects of central enterprises in the construction industry, improve the safety management level and prevent accidents, according to the requirements of the SASAC Mobilization Meeting for Safety Patrol Inspection of Major Dangerous Projects of Central Enterprises in the Construction Industry, on June 23, the third group of SASAC Safety Patrol Inspection of Major Dangerous Projects of Central Enterprises in the Construction Industry carried out a patrol survey of the Jinjiang Cultural and Creative Industry Center Phase I Project of the Third Company of China Construction Fifth Engineering Bureau.
The Project Department, through continuous exploration and building of smart construction sites, applies the real name system of labor service, dust monitoring, VR safety education, foundation pit settlement monitoring, high formwork monitoring, unloading platform load monitoring, etc.
Later, the inspection team inspected the 5G+smart exhibition hall, quality and safety management, process model, delivery model, basement electromechanical fire protection integrated pipeline, basement waterproof pump room and other areas.
Jinjiang Cultural and Creative Project is a typical project of China Construction Fifth Engineering Bureau in the field of green construction and rapid construction.
Based on their own work experience, the members of the expert group guided the construction of the project site from the aspects of dangerous large projects, temporary power supply, large equipment, and scheme management, and gave targeted tips on key risk hidden dangers and their control measures.
This year, China Construction Fifth Engineering Bureau established five inspection teams, which have completed the inspection of 156 projects and eliminated more than 3000 hidden dangers.
as the core quality and safety smart management system.
The scheme disclosure and safety technical disclosure shall cover the front-line construction personnel, actively promote the information safety management, and improve the timeliness, accuracy and efficiency of the scheme disclosure# 03 The on-site safety measures should be put in place to ensure the adaptability of the implementation of the scheme.