Circular on the first comprehensive inspection of the construction market in Jurong in 2022


2.

A few project construction unit project managers and other on-site management personnel are not on duty and do not perform their duties in place; The implementation of migrant workers’ system is not in place, and some important project control data (supervision meeting minutes, construction organization design plan, etc.) that should be signed by the project manager should be signed by others.

2、 There are the following problems in the construction procedures, market behavior, project quality, safety and civilized construction of some projects: (I) the procedures for changing personnel in key positions of some projects in market behavior are not handled in a timely and standardized manner, and the phenomenon of “performing duties before changing” exists in the change of project managers.

It mainly includes: project construction application procedures, project entity quality control, seismic fortification, safety production, civilized construction, site dust control, general subcontract management, supervision behavior, and on-site performance of project management personnel at the construction site; The implementation of project quality and safety improvement actions by all parties involved in the construction, and the implementation of special rectification work of bidding for government invested housing construction and municipal engineering projects; The implementation of the projects under construction “real name system for migrant workers, special account for migrant workers’ wages, full monthly payment of migrant workers’ wages, migrant workers’ wage deposit” and “notice board for general contracting and rights protection information”; Implementation of green building and prefabricated building schemes of all parties involved in the construction; The implementation of epidemic prevention and control and anti underworld and anti evil in the field of engineering construction.

(4) The approval of the special construction plan for safety and civilized construction is not in place, the detection of steel pipes, safety nets and labor protection supplies is not in place, and the management of mechanical equipment is not in place; Inadequate protective measures for high-altitude operation; The management of temporary construction electricity is not in place; Dust control is not in place.

constructed by Jurong yinpeng construction and installation engineering company; 3.

52), from June 6 to June 22, 2022, our bureau carried out a comprehensive inspection of the projects under construction in the city.

The management of project data in the early stage of some projects is chaotic, and there is a lack of unified classification.

The witness and sampler of the construction material inspection of the inspection batch are not in place; The inspection of building materials and commercial concrete is unqualified, and the supervision is not strict; Some project supervision units are lax in the review of the special quality and safety construction scheme of the construction unit, the qualification review of the personnel of the project Department of the construction unit and the supervision of on-the-job performance; The supervision materials are signed by the director, and the supervision rules are not targeted and professional; The supervision monthly report, supervision log, on-site record, parallel inspection, meeting minutes, supervision notice and other data files are not standardized.

Halfen Frimeda

The above-mentioned units criticized in a circular will be recorded in the bad behavior records of construction enterprises, and points will be deducted in the credit system of Zhenjiang construction enterprises..

3、 Handling opinions (I) the following five construction units shall be notified and praised throughout the city.

Yunzhu community 5 #-10 #, 21 #-23 # building, underground garage II and civil air defense basement project constructed by Jiangsu Jintu Construction Group Co., Ltd; 4.

1 The 32-35 #, 38-41 #, 45 #, 46 #, underground garage (4-16 axis intersecting A-S axis) project of Baiyue Huafu block B constructed by Nantong No.5 construction Yuejin construction and Installation Engineering Co., Ltd.

1 The Yangtze River water diversion project constructed by China Construction Installation Group Co., Ltd.

(3) Some project directors and professional supervisors of the project supervision behavior are not on duty, the supervisors are inconsistent with the filing personnel of the project construction system supervision contract, the change of supervisors is not applied for and entered into the system in time, and the supervision contract is not filed.

Notice on the first comprehensive inspection of the construction market in Jurong in 2022.

A total of 46 project lots were inspected during the comprehensive inspection of the construction market.

The road engineering project of Baiyue Huafu area in Jurong City constructed by Jiangsu Shanshui Environmental Construction Group Co., Ltd; (2) The following construction units and supervision units will be criticized in a circular throughout the city.

(5) Some projects of green buildings and prefabricated buildings did not strictly implement the “model room” advance system of green buildings.

Some project PC components have not gone through the filing procedures, and the filing registration is not in place.

Before the energy-saving construction, the thermal insulation and energy-saving construction did not meet the design requirements, and the “model room” containing thermal insulation system, door and window system, sound insulation system and other contents was not made as required and entrusted to the testing agency for testing.

The inspection is now reported as follows: first, basic information this major inspection activity mainly inspects the market behavior, on-site management, physical quality, safety, implementation of green buildings and prefabricated buildings of all parties involved in the construction of projects in the city, as well as the implementation of epidemic prevention and control and anti Mafia and anti evil in the field of engineering construction.

and the EPC project of Jurong No.

The reconstruction and expansion project of the party masses Service Center in beiyangmen community, Huayang Street – the office building project of the party masses Service Center constructed by Jiangsu huawang Construction Group Co., Ltd; 5.

1 water plant; 2.

The 32-35 #, 38-41 #, 45 #, 46 #, underground garage (axis 4-16 intersects axis A-S) project of plot B of Baiyue Huafu supervised by Zhenjiang Huapu Construction Supervision Co., Ltd.

The 3 #, 4 #, 7 #, 9 # production workshops, 5 #, 6 # warehouses and 8 # office building projects of Jiangsu Jindian Industrial Co., Ltd.

(2) Project quality behavior some project construction units do not strictly control the project quality, and the quality responsibility system is not perfect; The collection of construction technical data and quality assurance data of the construction project cannot keep up with the image progress of the project; If the construction materials and commercial concrete fail to pass the inspection, the next process construction will be carried out without timely supervision and implementation of rectification; The quality management of some physical projects is not in place, and the control measures for common engineering quality problems are not fully implemented; The rectification of unqualified concrete strength is not timely, and the concrete sampling inspection of the project entity is unqualified.

All construction, construction and supervision units and relevant departments under the Bureau: according to the notice on carrying out the first comprehensive inspection of the construction market in Jurong in 2022 (Ju Zheng Jian Zi [2022] No.