Mobilization records of materials, components and accessories: 40 cubic meters of aerated block and 2 tons of high-strength shrinkage grouting material (floor reinforcement).
Production records: carpentry: 11 persons, the light steel keel partition wall on the seventh floor is sealed with one-sided gypsum board, the antirust paint on the conversion layer is applied, the light steel keel partition wall on the third floor is sealed with one-sided gypsum board, bricklayer: 18 persons, plastering on the fourth floor, wall building on the fifth and sixth floors, electrician: 13 persons, on-site inspection, drainage electrician, casing reinforcement team: 5 persons West toilet ground reinforcement weak current team: 2 people, weak current casing handling on site: 6 people, transfer and supplement materials on each floor, Site cleaning and transportation} construction progress: 30% of the carbon fiber reinforcement on the ground of the second, third, fourth and fifth floors, 65% of the light steel keel partition wall on the fourth floor, 80% of the wall masonry on the fifth and sixth floors, 80% of the light steel keel partition wall on the seventh floor, and 80% of the technical quality and safety work records: safety and technical disclosure of each team every day, confirmation of the construction scope and relevant safety precautions of the day, safe and civilized construction, Ensure project quality.
Pre shift Education: Hydropower team, reinforcement team, bricklayer team, handling team..
Coordination matters: no coordination matters at present.