Construction project completion acceptance process / procedures / necessary conditions / filing, too complete


07 completion acceptance the construction unit shall preside over the completion acceptance meeting and organize the acceptance parties to inspect the project quality

.

Within five days after the acceptance is qualified, the supervision organization shall submit the supervision report to the county housing and Urban Rural Development Commission

.

The survey and design unit shall inspect the survey and design documents and the design change notice signed by the design unit during construction, and submit a written quality inspection report, which shall be reviewed and signed by the project leader and the unit leader

.

The construction unit shall rectify according to the rectification opinions put forward by the acceptance parties and the notice of order for rectification

.

The construction unit shall be responsible for applying to relevant government administrative departments or authorized testing institutions for various disciplines System acceptance: 1) fire control acceptance document 2) planning acceptance approval document 3) environmental protection acceptance approval document 4) elevator acceptance document 4) relevant acceptance documents of Intelligent Building 5) pre acceptance opinions on construction project completion archives 6) indoor environment test report of construction project IV The construction unit shall handle the project completion acceptance filing with the filing authority within 15 working days after the project completion acceptance is supervised and inspected by the project quality supervision organization and meets the requirements

.

After the agreement is reached, the project completion acceptance shall be re organized

.

6

.

The supervisors shall participate in the review of important rectification contents

.

① The construction, survey, design, construction and supervision units shall respectively report the performance of the project contract and the implementation of laws, regulations and mandatory standards for project construction in all links of project construction; ② Review the project archives provided by the construction, survey, design, construction and supervision units; ③ Check the physical quality of the project; ④ Make an overall evaluation on project construction, equipment installation quality and various management links, form project completion acceptance opinions, and the acceptance personnel shall sign

.

02 the supervision unit shall submit the project quality evaluation report

.

13) Other documents required by laws, regulations and rules.

.

3、 Necessary conditions for project completion acceptance 1

.

The inspection data related to safety and function of divisional works included in unit works are complete; The spot check results of main functional items meet the provisions of relevant professional quality acceptance specifications

.

Source: after the completion of the completion of the registration, all the project groups of the original version of the network version have summarized the process and contents of the completion check and acceptance of the project

.

2、 Procedures for project completion acceptance 1

.

The unqualified project shall be re accepted after rectification according to the unified standard for construction quality acceptance of building engineering and other acceptance specifications until it is qualified

.

For the project under supervision, the project completion report must be signed and commented by the chief supervision engineer( Before the completion of the project, the construction unit shall notify the quality supervision department to carry out in place quality supervision and inspection on the project entity)

.

of the project completion acceptance

.

03 the survey and design unit shall submit the quality inspection report

.

After the rectification, the construction unit shall write the rectification report, which shall be sent to the quality supervision station after being signed and sealed by the construction, supervision, design and construction units

.

After passing the preliminary inspection, the construction unit shall submit the project completion report to the construction unit

.

The essence of the enrichment is shown below and shared with the engineering friends

.

After the project is completed, the construction unit shall submit the project completion report to the construction unit and apply for project completion acceptance

.

Put forward rectification opinions in case of quality problems

.

12) Commercial houses shall also submit the “residential quality assurance” and “residential use instructions”

.

2

.

08 the construction unit shall rectify according to the acceptance opinions

.

09 the project is accepted as qualified

.

The divisional (sub divisional) works included in the unit project have passed the acceptance and comply with laws, regulations, mandatory standards for project construction, provisions of design documents and contract requirements; 3

.

1、 Completion acceptance process “Ten Steps” 01 self inspection and evaluation of the construction unit after the completion of the unit project, the construction unit shall inspect the quality of the project, fill in the project acceptance report after confirming that it meets the design documents and contract requirements, and sign it by the project manager and the person in charge of the construction unit

.

The construction unit shall provide the following documents when handling the filing procedures of the completed project: 1) completion acceptance filing form; 2) Project completion acceptance report; 3) Construction permit; 4) Review comments on construction drawing design documents; 5) Project completion report submitted by the construction unit; 6) Project quality evaluation report submitted by the supervision unit; 7) Quality inspection reports submitted by survey and design units; 8) Approval documents or permission documents issued by planning, public security, fire protection, environmental protection and other departments; 9) Opinions on project completion acceptance signed by the acceptance team; 10) Project quality warranty signed by the construction unit; 11) Summary of unit project quality acceptance

.

04 the construction (supervision) unit shall organize the preliminary inspection, and the construction unit shall organize the supervision, design, construction and other units to conduct the preliminary inspection and acceptance of the project quality

.

The members of the acceptance team shall have corresponding qualifications

.

All special acceptance and acceptance of relevant professional systems have passed

.

The construction unit shall notify the project supervision organization responsible for supervising the project of the time, place and list of acceptance teams seven working days before the completion acceptance of the project

.

The appearance quality of unit works meets the requirements

.

All parties shall put forward rectification opinions on the existing problems, the construction unit shall fill in the rectification report after the rectification is completed, and the supervision unit and the supervision team shall verify the rectification

.

3

.

The engineering data meet the requirements; 4

.

The construction unit shall submit the complete engineering technical data to the quality supervision department for inspection seven days in advance

.

06 the construction unit shall submit the engineering technical data

.

After receiving the project completion report, the construction unit shall organize the survey, design, construction, supervision and other units and experts from other relevant parties to form an acceptance team and formulate an acceptance scheme for the project that meets the completion acceptance requirements

.

5

. Magnetic Steel Chamfer

The construction unit shall organize the completion acceptance of the project

.

4

.

After receiving the project completion report, the owner shall organize relevant personnel of the design, construction, supervision and other units to establish an acceptance team

.

The construction unit shall report to the county housing and Urban Rural Development Commission for the record according to relevant regulations

.

10

.

If the construction, survey, design, construction, supervision and other parties involved in the project completion acceptance cannot reach an agreement, they shall report to the local construction administrative department or supervision organization for coordination

.

Completed design and various contents specified in the contract; 2

.

The supervisors of the supervision department shall go to the construction site to supervise the organization form, acceptance procedures, implementation of acceptance standards, etc

.

If the project is large or complex, an acceptance scheme shall be prepared

.

After receiving the project acceptance report, the supervision unit shall comprehensively review the acceptance data of the construction unit, sort out the supervision data, evaluate the project quality, and submit the project quality evaluation report, which shall be reviewed and signed by the director and the person in charge of the supervision unit

.

05 the owner shall form an acceptance team and determine the acceptance scheme

.

Tags:

Related Post