[jianjiantong] 6 dead and 6 injured! A major accident occurred at a construction site in Zhejiang!


After the accident, the leading comrades of the provincial Party committee and the provincial government attached great importance to it and made important instructions successively.

An independent warehouse shall be set up for paints, coatings and hazardous chemicals, which shall be in the charge of a specially assigned person.

  IX   The erection of scaffold and support system must comply with relevant current standards such as technical code for safety of fastener steel pipe scaffold jgj130 and technical code for safety of bowl buckle steel pipe scaffold in construction jgj166.

III   Strictly implement the preparation regulations and approval system of the company’s relevant special plans.

The materials of steel pipe and fastener must comply with relevant standards, and on-site sampling inspection and retest shall be carried out as required to ensure conformity.

During construction, tools and materials that are easy to fall shall be equipped with tool bags or placed in a reliable position to prevent falling.

As of 8:00 on November 25, 6 people were killed and 6 injured.

Ensure that the fire passage is unblocked, and occupation is strictly prohibited.

The construction unit shall prepare a special scheme before the construction of divisional and subdivisional works with high risk; For divisional and subdivisional works with greater risk exceeding a certain scale, the construction unit shall organize experts to demonstrate the special scheme.

When multiple equipment operate at the same time, they shall cooperate with each other.

There is a large amount of welding work in the grid project.

The project shall strictly approve the hot work and put forward specific fire prevention requirements..

  Xi   Sufficient fire-fighting equipment shall be provided on site and shall be effective.

Timely distribute personal labor protection articles and regularly check the use.

  IV   According to the construction characteristics of grid engineering, the on-site risks are identified and analyzed, and the key points of safety management are put forward.

Formulate effective management measures in combination with each key point of safety management.

X   No processing area shall be set under and around the grid, and a large number of personnel shall not be arranged under the grid for construction.

Other safety measures shall be supplemented and improved according to the actual situation.

Before the operation, there must be safety technical disclosure records and sign the procedures.

Safety management requirements for steel structure grid engineering I   According to the regulations on safety management of high-risk divisional and subdivisional works issued on February 12, 2018, (I) the installation works of steel structure, grid frame and cable membrane structure belong to the scope of high-risk divisional and subdivisional works, (II) the installation works of steel structure with span of 36m and above, Or the installation of space truss and cable membrane structure with a span of 60m and above belongs to the scope of divisional and subdivisional works with greater risk exceeding a certain scale.

Fixing Socket Cross Hole Nail Plate

The process arrangement shall try to avoid cross operation up and down.

It is a community commercial complex integrating shopping, dining, entertainment, accommodation and neighborhood supporting projects.

The organization and emergency procedures of the plan must conform to the reality, conduct drills regularly, and constantly improve the shortcomings of accident handling procedures.

Your city should deeply draw lessons from the accident, draw inferences from one instance, and pay close attention to the rectification of potential problems.

Office of Zhejiang Work Safety Commission     According to the official WeChat official account of Jinhua economic and Technological Development Zone in November 25, 2021, “lakeside” is located in the lake and seawall area of Jinhua economic development zone.

Before the accident is closed, the accident investigation report (not finalized) shall be submitted to the Provincial Safety Commission Office for review and approval, and your city shall be responsible for approving and closing the case and publishing it to the public; After the case is closed, the implementation of the accident investigation report and accident handling decision shall be reported to the provincial safety committee office for filing in time.

Your city shall, in accordance with the provisions of Zhejiang Province on the reporting, investigation and handling of production safety accidents and other relevant provisions, immediately organize and carry out accident investigation, quickly find out the cause of the accident, study and put forward handling opinions in strict accordance with the requirements of the provisions on accident investigation.

and is planned to be ready for trial operation in August 2022.

Jinhua Municipal People’s Government: on November 23, 2021, a major steel structure collapse accident occurred at the construction site of “hubinli” project in Jinhua development zone.

The driver, signal commander and rigger must work with certificates.

On November 25, the emergency management department of Zhejiang Province issued a notice on listing and supervision of investigation and handling of major production safety accidents, which showed that on November 23, 2021, a major steel structure collapse accident occurred at the construction site of “hubinli” project in Jinhua development zone.

It is understood that the office of Zhejiang work safety committee has asked Jinhua City to immediately organize an investigation, quickly identify the causes, study and put forward handling opinions in strict accordance with the requirements of accident investigation regulations.

After research, the provincial safety committee office decided to supervise the investigation and handling of the major accident.

Construction shall not be arranged without the approval of relevant personnel or departments.

Before lifting operation, fully consider the surrounding environment of the operation area, eliminate adverse factors and do a good job of warning.

Contact person and Tel.: Zhou Chengcheng, 0571-87055020.

The project is constructed by Jinkai Industrial Development Group Co., Ltd.

Before operation, written safety technical disclosure must be made to all employees of the construction team and filed.

The Provincial Construction Commission Office is requested to strengthen business guidance and urge Jinhua City to seriously carry out accident investigation, cause analysis and other related work.

If it is really unavoidable, effective isolation and protection measures shall be taken, and a special person shall be assigned to take charge (supervision).

Key areas such as welding and cutting operation area, wood stacking area, material warehouse, dormitory area and other parts must be monitored.

V   Prepare the emergency rescue plan for production safety accidents on the construction site, analyze the severity of various accidents and consequences easily caused by grid construction, and formulate targeted preventive measures.

Before hoisting, the mechanical performance of the crane can be used only after passing the acceptance.

Your city should deeply draw lessons from the accident, draw inferences from one instance, and pay close attention to the rectification of potential problems.

Everyone is responsible for safe production! This is a sentence that we engineers should keep in mind all the time.

The foreman who arranges the construction must make pre shift disclosure to the cross operators, clarify the construction scope of both parties, and inform the operators of the potential safety hazards and dangerous preventive measures in the construction parts.

VII   Safety net, safety belt, safety helmet and other protective articles shall go through the mobilization acceptance procedures and can be used only after they are qualified.

Every time this disaster happens, Xiaobian’s heart will become extremely heavy.

The planned land is 42 mu, with a total construction area of about 100 thousand square meters.

After the accident, relevant personnel must report level by level as required   Vi   Adhere to “prevention first”, formulate various management measures in combination with special schemes and identified hazard sources, and focus on the safety prevention measures for collapse (steel structure, support system and scaffold), lifting injury, falling from height, object strike (falling objects) and electric shock.

The lifting operation must strictly abide by the operating procedures and strictly implement the “ten no lifting”.

  II   Before the implementation of special schemes such as grid construction, hoisting operation, scaffold and support system, the project technicians shall make safety technical disclosure to the on-site management personnel and operators.

Fireworks are strictly prohibited on the construction site and in the reservoir area.

Anti climbing measures shall be taken for the scaffold and support system, and independent access roads shall be set up.

During construction, the grid structure shall be monitored and recorded, and treatment measures shall be taken immediately in case of hidden dangers.

The total investment is more than 900 million yuan.

The team leader must make a pre shift speech and reasonably allocate the work contents of the personnel.

As of 8:00 on the 25th, 6 people were killed and 6 injured.

After the accident, the leading comrades of the provincial Party committee and the provincial government attached great importance to it and made important instructions successively.

In case of an accident, to ensure the rapid and effective start of the plan, we must strive to minimize casualties and property losses in the shortest time.

Personnel shall stay away from areas prone to falling objects, and shall not stay under grid, scaffold and support system for a long time.

  VIII   The hoisting machinery must be driven and operated by qualified professionals.