[jianjiantong] defaulted on the project payment of RMB 80 million, and the general contractor was forced to shut down completely


The first and second phases of the project have been delivered.

Recently, a work stoppage notice was pasted on a construction site in Wuhan: the notice said that the construction content of Wuhan Yajule garden project contracted by our company has been basically completed.

“Wuhan Yajule garden” is the first project of Yajule in Wuhan.

Yajule officials have not made any response to the suspension announcement.

The resumption time is to be determined.

As the year is approaching, the construction of our project is nearly completed, and a large number of personnel salaries and materials and equipment need to be paid.

However, what is more outrageous is that this is not the first shutdown of Wuhan Yajule garden.

It is located at the intersection of Miaoshan 1st Road and Yanhu Road, Jiangxia District.

It is expected that more than 100 million progress payment will be generated from this month to the Spring Festival, and the owner still has no feasible payment plan, so the advance pressure is huge.

Yajule group has made it clear that it can not guarantee the full payment of the project funds before the year.

If there is any infringement, please contact to delete!) Long press the QR code to follow us ▶▶▶。.

At present, we are unable to continue the advance construction of the project to ensure the completion filing and normal delivery.

It decided to close the gate of the construction site from November 4 and prohibit any personnel from entering and leaving.

Since this year, Yajule group has been unable to pay our project funds normally according to the contract, and the project funds owed to us are up to more than 80 million yuan.

(source: integrated on the Internet, the picture and copyright belong to the original author.

As early as November 4, a “shutdown notice” was posted on the construction site of Wuhan Yajule garden project, in which the amount of arrears involved was quite serious.

By the end of October, the output value of the third phase had reached more than 90%; However, the unpaid progress payment has reached 100 million yuan.

The notice showed that the first phase of general contracting had been completed and filed in 2019, and the second phase was completed and filed on New Year’s day this year.

At present, the third, fourth and fifth phases are under construction.

U Bar Anchor

The general contractor will negotiate the repayment with each labor team and supplier.

The general contractor was forced to stop work.

As a result, the material payment and migrant workers’ wages could not be paid in time, resulting in the suspension of supply and shutdown of a large number of material suppliers and labor services.

Tags:

Related Post