In early September, I saw in the owner group that someone sent photos of the two buildings getting closer and closer.” the owner, Miss Chen (pseudonym), told reporters, There was a certain distance between the bottom of building 4 and building 3.
Liang (pseudonym), sent the third-party testing company’s “testing and identification conclusions and suggestions” to the reporter.
(source: integrated on the Internet, the picture and copyright belong to the original author.
On September 27, relevant experts went to the site to demonstrate, and then issued a document, “at present, the inclination of 3#, 4# buildings does not affect the safety and normal use of the structure.” “I bought the Hongwan community house in 2017 and usually live in other places.
Huidong County government said that it had quickly started the emergency response procedures, ordered the developers to evacuate the residents of two buildings, suspended all external business, evacuated and resettled 277 people from 126 households, and established an emergency response working group to carry out deformation observation.
Mr.
She is worried about potential safety hazards.
It is pointed out in the expert argumentation opinions and expert argumentation opinions of Baidu network disk members in the reference to engineering practice in 2021 that the inclination of the current 3#, 4# buildings does not affect the safety and normal use of the structure.
Recently, in phase II of Hongwan community, shuangyuewan, Huidong, Guangdong, many residents reported that the roofs of two buildings in the community were inclined.
According to the preliminary feedback of the provincial general station company, the maximum displacement of the top of a single building of the two buildings is about 10 cm, about one-third of the maximum allowable value in the specification.
On September 23, Guangdong construction engineering quality and safety inspection station Co., Ltd.
The expert argumentation opinions are as follows: according to the expert argumentation opinions, Huidong County will continue to do a good job in house observation, urge developers to fulfill their main responsibilities and solve doubts to the owners.
No obvious crack is found in the structure of the 4# building, and no obvious damage is found in the structure.
Test conclusion the third-party testing company suggests that the joint spacing does not meet the regulations, and technical treatment should be carried out.
For this test report, many owners do not recognize it.
The two buildings are closer and closer together.
As they reached the top, the two buildings became more and more inclined.
The house has 70 years of property rights and is close to the sea.
At the same time, the developer was urgently informed in writing, requiring the developer to immediately organize the original five responsible subjects to carry out research and judgment analysis, and immediately organize technical forces to carry out settlement observation on the two buildings.
The county also immediately carried out building deformation observation, ordered and urged developers to quickly entrust a qualified third party to carry out relevant testing work, and observed the deformation of the current inclination and vertex displacement of the two buildings.
If you can’t rest assured, it’s more difficult to rent and sell.
before September 25).
gave inspection conclusions and suggestions.
If there is any infringement, please contact to delete!) long press the QR code to follow us ▶▶▶。.
On September 23, Guangdong construction engineering quality and safety inspection station Co., Ltd.
Huidong County government said that the next step of disposal will be carried out after the handling opinions of the preliminary analysis results of the testing company come out.
At present, the developer has entrusted Guangdong HaiYe Geotechnical Engineering Co., Ltd.
concluded that the maximum inclination values (including construction errors) of the superstructure of 3#, 4# buildings were H / 1076 and H / 937 respectively, which were less than the lateral displacement limit not suitable for bearing specified in the reliability appraisal standard for civil buildings.
The treatment suggestions are: 3#, 4# building tops collide, and the joint spacing does not meet the provisions of seismic joint width in code for seismic design of buildings (gb50011-2010), so technical treatment should be carried out.
According to the technical specifications and workflow, the preliminary analysis results are expected to be issued within 15 days (i.e.
The owner, Mr.
to carry out settlement observation once a day.
3.
Who will compensate for the loss? “The person in charge of the property said that next, well-known experts in the province demonstrated the test conclusion again, and then decided whether to resume the occupancy of the building.” on September 28, Huidong issued a document saying that Huidong County attached great importance to and acted quickly after the masses reported the problem of house inclination in baoanhong Bay phase II 3# and 4# buildings in Huidong County on September 6, On September 9, a qualified third-party organization was entrusted to carry out settlement observation and deformation observation, and experts were organized to demonstrate on September 27.
(hereinafter referred to as “provincial station company”) to carry out deformation observation.
The reporter learned that Huidong County Government quickly started the emergency response procedures, and the housing and Construction Department organized technicians and invited experts from the Provincial Academy of Building Sciences to carry out preliminary investigation at the scene at the first time.
The two buildings are more and more closely “bonded” together.
Liang believes that this is only a test of the current house quality.
Looking up from the downstairs, you can see 3 buildings on the 32nd floor and 4 buildings on the 30th floor.
At present, the developer has entrusted Guangdong construction engineering quality and safety inspection station Co., Ltd.
It often has to face typhoons and potential safety hazards.