189) is formulated in accordance with the relevant provisions of the “Regulations on Quality Management of Construction Projects” to strengthen the management of on-site supervision of housing construction projects and ensure project quality.
The on-site supervision plan should be sent to both the construction unit and the construction enterprise, and a copy should be sent to the construction administrative department or its entrusted engineering quality supervision agency in the location of the project.
Article 3: When preparing supervision plans, supervision enterprises shall formulate a site supervision plan, clarifying the scope, content, procedures, and responsibilities of site supervision personnel.
Article 1 of the “Management Measures for Onsite Supervision of Housing Construction Projects (Trial)” (Jian Shi [2002] No.
Article 5: Under the guidance of the Chief Supervision Engineer, on-site supervision personnel shall be responsible for the specific implementation of on-site supervision.
Article 2: The on-site supervision of housing construction projects referred to in these Measures (hereinafter referred to as “on-site supervision”) refers to the on-site supervision activities carried out by supervisory personnel during the construction phase of housing construction projects, to supervise the construction quality of key parts and processes throughout the entire process.
The key parts and processes of the housing construction project specified in this method include: earthwork backfilling, pouring of concrete cast-in-place piles, pouring of concrete for underground continuous walls, soil nail walls, post pouring strips and other structures, pouring of waterproof concrete, treatment of the detailed structure of the waterproof layer of the coiled material, and installation of steel structures in terms of basic engineering; The main structural engineering includes: concealed process of beam column node reinforcement, concrete pouring, prestressed tensioning, prefabricated structure installation, steel structure installation, grid structure installation, cable membrane installation.
Article 6: The main responsibilities of on-site supervision personnel are: (1) to inspect the on-site quality inspection personnel of the construction enterprise, the certified personnel of special types of work, and the preparation of construction machinery and building materials; (2) Supervise the implementation of construction plans and mandatory standards for key parts and processes on site through on-site supervision; (3) Verify the quality inspection reports of incoming building materials, building components, equipment, and commercial concrete, and supervise the construction enterprise on site for inspection or entrust a qualified third party for re inspection; (4) Keep on-site supervision records and diaries, and preserve the original materials of on-site supervision
.
Article 4: According to the on-site supervision plan formulated by the supervising enterprise, the construction enterprise shall notify the project supervision organization dispatched by the supervising enterprise to the construction site in writing 24 hours before the construction of key parts and processes that require on-site supervision.
The project supervision agency shall arrange on-site supervision personnel to implement on-site supervision according to the on-site supervision plan.