The Ministry of housing and urban rural development once again made it clear that the audit conclusion should not be used as the basis for


Urge the construction unit to ensure the reasonable construction period of the project, and prohibit blindly rushing for the construction period and catching up with the progress.

For the projects to be reopened in the near future, simplify the requirements of the procedures related to project quality and safety, optimize the procedures related to project quality and safety, encourage the implementation of the notification and commitment system, strengthen post event supervision, and allow the relevant procedures to be completed after the epidemic is eliminated.

Previously, on February 26th, 2020, the general office of the Ministry of housing and urban rural development issued the notice on strengthening the prevention and control of the COVID-19 and orderly promoting the resumption of work of enterprises, which clearly required that the settlement of project prices should be standardized, the audit conclusions of the audit institutions should not be used as the basis for project settlement of government and state-owned investment projects, and the construction unit should not refuse or delay the settlement of projects and the payment of project funds on the grounds that the final account audit has not been completed.

The original text is as follows: Notice of the general office of the Ministry of housing and urban rural development on strengthening the prevention and control of the COVID-19 and orderly promoting the resumption of work of enterprises Jian ban Shi [2020] No.

Low risk areas should comprehensively promote the resumption of enterprises and engineering projects, medium risk areas should orderly promote the resumption of enterprises and engineering projects in stages and at wrong times, and high-risk areas should ensure that the scope of enterprises’ resumption of work can be gradually and orderly expanded after the epidemic has been effectively prevented and controlled.

If the security deposit is not returned in accordance with the provisions or the contract, the security deposit receiver shall pay liquidated damages for overdue return to the enterprise.

The local competent departments of housing and urban rural construction at all levels should strengthen the “four senses”, firm the “four self-confidence”, achieve the “two maintenance”, effectively improve their political position, carry out the overall situation of enterprise operation and project construction under the unified leadership of the local Party committee and government, and strengthen the classified guidance according to the local epidemic prevention and control requirements, and orderly promote the commencement and resumption of enterprises and projects with the county (city, District, banner) as the unit.

Projects involving epidemic prevention and control, people’s livelihood security and other important national and people’s livelihood should be given priority to start and resume work, and the commencement and construction of major projects should be accelerated, and “one size fits all” is prohibited.

Strengthen the main responsibilities of enterprises, clarify the main responsibilities of all parties on the construction site of the resumed project, strictly implement various epidemic prevention measures, effectively ensure that no major epidemic events occur after the resumption of work, and fully serve the overall situation of national epidemic prevention and control.

The construction unit shall pay the project funds in full and on time in accordance with the contract, and no new arrears shall be formed.

Government and state-owned investment projects shall not take the audit conclusion of the audit institution as the basis for project settlement, and the construction unit shall not refuse or delay the settlement and payment of the project on the grounds that the final account audit has not been completed.

(2) Earnestly implement the requirements of epidemic prevention and control.

Urge enterprises to implement the main responsibility of safety production, strengthen the inspection of safety production conditions before the resumption of construction projects, focus on the investigation of safety hazards of divisional and subdivisional works with high risks, such as deep foundation pits, lifting machinery, high formwork and urban rail transit projects, strengthen the disclosure of quality safety, health and epidemic prevention before the resumption of construction of personnel entering the site, and deal with engineering projects with insufficient preparation, inadequate preventive measures and inadequate hidden danger treatment, It is strictly forbidden to resume work without authorization.

The local competent departments of housing and urban rural construction at all levels should actively strengthen the overall planning and coordination with the local competent departments of health and disease control, formulate and issue guidelines for epidemic prevention and control and resumption of work of construction projects according to the actual situation, put forward clear requirements for enterprise organization and management, personnel gathering management, personnel screening, closed management, on-site epidemic prevention material storage, health and safety management, emergency measures and other aspects, and refine epidemic prevention and control measures, Assist enterprises to solve the problems of preventing and controlling material shortages.

The construction period is delayed due to epidemic prevention and control, which belongs to the force majeure situation agreed in the contract..

5, housing and urban rural development departments of all provinces and autonomous regions, housing and construction (Management) committees of municipalities directly under the central government, housing and Urban Rural Development Bureau of Xinjiang production and Construction Corps, relevant industry associations, and relevant central enterprises: first, firmly establish the awareness of the overall situation, Orderly promote the resumption of work of enterprises (I) promote the resumption of work of enterprises and projects by regions and levels.

(5) Strengthen the management of contract performance changes.

Vigorously promote project guarantee, and replace the deposit with bank guarantee, project guarantee company guarantee or project guarantee insurance to reduce the occupation of enterprise funds.

During the epidemic prevention and control period, new construction projects may temporarily not collect migrant workers’ wage deposits; The bid security, project quality security and other security can be in the form of bank guarantee or deferred payment in combination with the local actual situation.

(3) Strengthen the quality and safety management of the construction site.

Strictly implement the system of enterprise related fee list, resolutely stop all kinds of arbitrary charges, fines and apportionment, and effectively reduce enterprise costs.

Solid Lifting Socket Cross Pin

Accelerate the promotion of bank enterprise cooperation, and encourage commercial banks to support enterprises with excellent credit rating in terms of credit line, pledge financing, loan interest rate, etc., so as to effectively reduce the financing cost of enterprises.

The local competent departments of housing and urban rural construction at all levels should strengthen the supervision of project quality and safety during the commencement and resumption of work, strengthen risk research and judgment, formulate countermeasures, innovate the supervision mode, and strictly prevent quality and safety accidents.

2、 Increase support and solve the actual difficulties of enterprises (4) strictly implement the policy of stable growth.

For the management personnel who cannot return to their posts due to the epidemic, the enterprise is allowed to arrange other personnel with corresponding qualification certificates to take up their posts temporarily, so as to speed up the resumption of the project.

Source: the official website of the Ministry of housing and urban rural development, construction management and construction technology the Ministry of housing and urban rural development issued a notice again, clearly stating that it is strictly prohibited for the government and state-owned investment projects to require the construction unit to contract with capital in various ways.

Strictly implement the relevant provisions of the security deposit in the field of engineering construction, and the security deposit shall be returned in time when it expires.

The local competent departments of housing and urban rural development at all levels shall, together with relevant departments, establish a special assistance mechanism for enterprises to respond to the epidemic, conscientiously implement the relevant national fiscal, tax, financial, social security and other support policies, and guide enterprises to make full use of the preferential policies such as delayed payment or reduction of taxes, phased deferred payment or appropriate return of social insurance premiums, reduction and exemption of housing rents, and increase subsidies for staff skills training.