The most complete process of construction project completion acceptance is absolutely useful!


I hope the following contents can help you.

relevant quality inspection and functional test data of municipal infrastructure; (6) Planning acceptance approval documents; (7) Fire control acceptance documents or permit documents; (8) Environmental protection acceptance documents or permit documents; (9) The elevator acceptance permit and divisional acceptance documents issued by the supervision station; (10) Gas engineering acceptance documents; (11) Construction project quality warranty; (12) , regulations, rules and other documents required by regulations.

Engineering technical data (20 working days before acceptance); Supervision company (within 5 working days) (2) supervision company: prepare project quality assessment report (3) survey unit: prepare quality inspection report (4) design unit: prepare quality inspection report (5) construction unit: A.

The construction unit receives the filing form for completion acceptance of housing construction projects and municipal infrastructure projects from the filing authority.

main contents of site acceptance (1) the whole construction project has been completed according to the design requirements, meets the specified completion acceptance standards of the construction project, and submits the “project acceptance report” to the owner (general contractor) after being approved and signed by the supervision unit, and then the owner (General Contractor) organizes the design, construction, supervision and other units to carry out the completion acceptance of the construction project, and the intermediate completion of the single project for which the handover formalities have been handled, The completion acceptance will not be repeated.

After reviewing the engineering technical data, the supervision station evaluates the project and issues the construction safety evaluation of construction projects (the construction unit submits the engineering technical data to the supervision station for review 15 days in advance, and the supervision station returns the return form of project completion quality and safety management data to the construction unit within 5 days).

Source: as the last link of a construction project, the engineering data class and the completion acceptance of Zhulong supervision often fail to carry out the acceptance work due to data problems.

The principals of all parties involved in the completion acceptance shall sign on the completion acceptance report and affix their official seals..

the contractor prepares the construction project completion acceptance report to supervise the owner of the company.

V.

3.

Project completion pre acceptance (organized by the supervision company and participated by the owner and the Contractor): after the project is completed, the supervision engineer shall review the data and conduct on-site inspection according to the application form for unit project completion pre acceptance submitted after the Contractor’s self inspection and acceptance; The project supervision department puts forward written opinions on the existing problems, issues the supervision engineer’s notice (Note: fill in when necessary), and requires the contractor to rectify within a time limit; After the completion of rectification, the Contractor shall prepare the completion acceptance report of construction project according to the requirements of relevant documents, submit it to the supervising engineer for inspection, and submit it to the construction unit after the comments are signed by the project director.

2.

The construction unit, the construction unit, the supervision station and the filing authority shall each hold one copy.

preparation for construction project completion acceptance 1.

of project completion acceptance, And issue opinions on quality acceptance of construction projects.

b.

Magnetic Box Adapter

After receiving the written notice of project completion acceptance (the construction unit shall notify the supervision station in writing of the acceptance time, place and list of acceptance teams 7 days before the project completion acceptance, and attach the project quality acceptance plan), the supervision station shall review according to the review form of construction project completion acceptance conditions, and conduct on-site supervision on the organization form, acceptance procedures, implementation of acceptance standards, etc.

The filing authority shall, within 15 working days after receiving and verifying the filing materials, sign the filing opinions (seal) on the filing form for completion acceptance of housing construction projects and municipal infrastructure projects.

C.

d.

Quality qualification documents signed by survey, design, construction, supervision and other units; 5.

7 days before the completion acceptance of the project, the supervision station shall be informed in writing of the acceptance time, place and list of acceptance teams.

obtain special acceptance documents for planning, public security fire protection, environmental protection, gas engineering, etc.

To complete the design documents of the building construction project the various contents stipulated in the contract; 2.

filing procedures for completion acceptance of construction projects 1.

The following documents: (1) construction permit; (2) Review comments on construction drawing design documents; (3) Project quality evaluation report; (4) Engineering survey and design quality inspection report; (5) .

III.

Have complete technical files and construction management data; 3.

2.

The completion acceptance report of construction projects 2.

Project completion acceptance (organized and implemented by the owner, with the participation of engineering survey, design, construction, supervision and other units): (1) contractor: a.

There is a project warranty signed by the construction unit.

Vi.

The picture is from: the information prepared for the filing of the completion acceptance of construction projects (operated by the construction unit) in photo network 4: 1.

2.

Submit the engineering technical data and the review sheet of project completion quality and safety management data to the supervision station 15 days in advance (the supervision station shall return the return sheet of project completion quality and safety management data to the construction unit within 5 days).

I.

supervision on the completion acceptance of construction projects (operated by the supervision station) 1.

Elevator acceptance certificate issued by the supervision station.

Have the mobilization test report of main building materials, building components, fittings and equipment used in the project; 4.

b.

2 the requirements f the completion acceptance of a building construction project 1.

The construction unit shall submit the filing form for completion acceptance of housing construction projects and municipal infrastructure projects in quadruplicate and the materials specified above to the filing authority for filing with the official seal of the unit and the signature of the project leader of the unit.

(2) The owner (general contractor) shall organize the survey, design, construction, supervision and other units to check the project according to the completion acceptance procedures, and then make an acceptance conclusion and form a “project completion acceptance report”.