The total construction area is 220000 square meters! Tongzhou this key school welcome progress!


Renmin University of China has carried out the preparation of several special plans, including garden landscape, municipal roads and comprehensive pipe corridors, infrastructure, integrated design of road landscape, comprehensive utilization of underground space and civil air defense engineering, sponge City, smart campus, etc

.

At the same time, we also strive to achieve the consideration and balance of innovation, durability, economy, ecological and environmental protection in terms of building technology, materials and construction methods

.

Building height: ≤ 24m, local high point ≤ 36m, investment amount: 88.03 million yuan

.

Construction progress Renmin University of China, in accordance with the principle of “overall project approval and phased implementation”, cooperates with the construction of urban sub center to promote campus construction from west to East

.

East to Chunming West Road, South to Yunhe East Street, West to qianbeiying road and north to Zhaoshan street

.

The total investment of the project is 2159.89 million yuan, The total construction area is 222006 square meters

.

Previously, the design scheme of honor hall group project in Tongzhou new campus of Renmin University of China has also won the bid

.

That’s right! So today, Xiaobian will show you the latest progress of the school that has been mentioned n times

.

In August 2023, the campus can operate independently

.

The winning design includes the honor Hall of Tongzhou new campus of the National People’s Congress, the school building in the South District, the canteen in the west district and the public teaching building, with a total construction area of 101230m ², The aboveground area is 49265m ², Underground area 51965m ²。 It is reported that Renmin University will be located here, including the National People’s Congress business school, the school of finance, the school of economics, the school of Applied Economics, the school of statistics, the school of labor and personnel and the Hanqing Advanced Institute of economics and finance

.

The construction scale of phase I project is about 583000 square meters, and the construction contents mainly include: library, faculty building, public teaching building, public experimental center, student dormitory, canteen, concert hall, campus operation center, sports supporting facilities, municipal road infrastructure, etc., so as to ensure that the phase I Project can operate independently and meet the basic school running conditions, It is planned to be completed in 4 years

.

In terms of transportation, the completed projects include Metro Line 6, Batong line and suburban railway sub center line, which are close to dongxiayuan station and Lucheng station, which can meet the transportation needs of schools and central urban areas

.

These areas have one thing in common and are close to TongZhou campus of Renmin University

.

The construction site of phase I of South District school building and phase I of public teaching building: plot 6011, block 0902, sub center, with a construction area of 92030 m2   The total aboveground construction area is about 47265 square meters, of which the aboveground construction area of public teaching building phase I and Western canteen project is about 17523 square meters, and the aboveground construction area of South District school building phase I project is about 29742 square meters.; The total underground construction area is about 44765 square meters, of which the underground construction area of public teaching building phase I and Western canteen project is about 17000 square meters (3 floors underground), and the underground construction area of South District school building phase I project is about 27765 square meters (3 floors underground)

.

The construction area is 57644 square meters, and the aboveground construction area is about 28644 square meters

.

It is equipped with two-way six lane aboveground and underground systems, with a design speed of 60km / h on the ground and 80km / h underground

.

The construction site of phase I of the school building in North District: plot 6002, block 0902, sub center

.

It is expected that the second phase of the project will be completed by August 2025 and the whole campus will be fully completed

.

The underground construction area is about 29000 square meters

.

In April this year, the preliminary design and construction drawing bidding announcement of many projects such as the North District school building, the South District school building phase I, the public teaching building phase I, the student affairs center and the public teaching building phase II of Tongzhou campus of Renmin University was released..

.

City Planning Institute moved to TongZhou! The first municipal state-owned enterprise headquarters building to TongZhou! Guyuejiayuan replacement house in Lucheng town! Our TongZhou partners in the above major projects must be familiar with them

.

In the scheme, the streamline of students and teachers is vertically divided: the student public classroom is arranged in the lower floor area and underground space of the college building to evacuate a large number of people generated instantaneously; The teacher’s office and the comprehensive office of colleges and departments are arranged in the upper space, and a more private entrance and independent elevator are established for teachers, so as to create a more quiet and private office environment

.

At present, Renmin University is actively promoting new projects! In terms of transportation, the completed projects include Metro Line 6, Batong line and suburban railway sub center line, which are close to dongxiayuan station and Lucheng station, which can meet the transportation needs of schools and central urban areas

.

Building height: ≤ 24m, local high point ≤ 36m   Investment amount: 550.58 million yuan

.

Building height: ≤ 24m, local high point ≤ 36m; The investment amount is 729.01 million yuan

.

Combined with the different functions of phase I construction and the requirements of different use modes, different characteristic spaces and architectural shapes are created

.

It is a fast connecting channel between the central urban area and the urban sub center

.

  The total underground construction area is about 41000 square meters, of which the underground construction area of the student affairs center project is about 30000 square meters (3 floors underground), and the underground construction area of the public teaching building phase II project is about 11000 square meters (3 floors underground)

.

The activity square formed by the middle enclosure will be able to carry the large-scale gathering activities of the college in the future, and it is also a place for students’ daily communication

.

Construction site of phase II of North District student dormitory, canteen, student affairs center and phase II of public teaching building: plot 6002, block 0902, sub center, building area: 76332 m2, with a total aboveground building area of about 35332 m2, of which the aboveground building area of the student affairs center project is about 25000 M2 (4 ~ 5 floors above the ground), The aboveground construction area of phase II of the public teaching building is about 10332 square meters (4 ~ 5 floors above the ground)

. Steel Chamfer

This time, it involves phase I of the school building in the South District, phase I of the public teaching building and the canteen in the West District, phase II of the school building in the West District, phase I of the school building in the North District Campus operation center, student affairs center, phase II of public teaching building, etc

.

At present, Renmin University of China is actively promoting the new projects in this year and next, striving to complete the first phase of the campus project by August 2023, and the campus can operate independently to meet the needs of about 8000 students

.

The project starts from Yile West Road in the West and East Sixth Ring Road in the East, with a total length of 7.6km

.

Open, block oriented, pleasant scale, unified and changing architectural vocabulary, color, material texture

.

At present, the first construction project, North District student dormitory phase I, has been officially started in March 2019, with a construction area of 37000 square meters

.

According to the design scheme, the design team created a block campus layout; The street path creates a more flexible and convenient access experience for students and teachers

.

To find second-hand goods, go to Batong market [flea market]  /  House rental and sale  /  Housekeeping services] [business transfer  /  Looking for people and things  /  Pet information] [mother and baby supplies  /  Education and training  /  Second hand vehicles] [enter the homepage of Batong market].

.

The overall design presents the concept of “open block”

.

According to Xiaobian, the relevant websites recently released the latest bidding announcement for the whole process tracking audit consulting service of “TongZhou new campus of Renmin University”

.

Guangqu road extends to the East

.

At present, the scheme is continuing to deepen, and the construction is expected to start at the end of 2021

.

It is understood that the Tongzhou new campus of Renmin University of China plans to be implemented in two phases according to the principle of “overall project establishment and phased implementation”

.