17), which respectively clarified how to implement the new standard for policy housing projects such as new projects, one meeting three letter projects, and shared property housing How to implement the new standards and how to connect the old and new standards
.
Source: Beijing Municipal Commission of planning and natural resources on January 17, 2021, Beijing Municipal Commission of planning and natural resources issued the notice on further defining the time for the implementation of the new standard for the examination of construction drawings (sgzz [2021] No
.
In the process of project construction or approval, all units should strictly implement the corresponding specifications and standards
.
For new projects, the “construction project planning permit” shall prevail, and the new standard has been approved before the formal implementation The project of “construction project planning permit” (within the period of validity) can be examined according to the original standard
.
3、 The policy oriented housing projects, such as housing with common property rights, resettlement housing, public rental housing and collective land rental housing, should be appropriately relaxed, subject to the expert opinions on the review of affordable housing design scheme
.
If it involves infringement or the owner of the original right does not agree
.
Notice is hereby given
.
In view of the 6-month transition period from the release of specifications and standards to the implementation, relevant units should fully consider the project implementation cycle and specification implementation time to ensure the quality of project design
.
2、 For the project with three letters, the approval time of the “letter of opinion on design scheme review” shall prevail, that is, the project that has obtained the “letter of opinion on design scheme review” before the formal implementation of the new standard can be reviewed according to the original standard
.
The projects that have been organized and passed the review of affordable housing design scheme before the formal implementation of the new standard can be reviewed according to the original standard
.
All relevant units: in order to further clarify the implementation time of the standard, give consideration to the continuity of project construction and approval and the implementation of the new standard, after research, the time for the review and implementation of the new standard in our city’s construction drawing design documents is as follows: 1
.
Beijing Municipal Commission of planning and natural resources http://ghzrzyw.beijing.gov.cn/zhengwuxinxi/tzgg/sj/202101/t20210126_ 2232912.html some of the pictures in this article are from the Internet, and the copyright belongs to the original author and source
.